Ramona Municipal Water District

RAMONA MUNICIPAL WATER DISTRICT

0.88 MG Boulder Tank and Pipeline Project

Improving Your Water System’s Reliability

Description:

 A 0.88 MG Bolted Steel Tank and 12 inch Pipeline is under construction on an undeveloped area of Mount Woodson.  The 12-inch diameter polyvinyl chloride (PVC) pipe extends from South Woodson Drive, then south through an undeveloped area to Mount Woodson Rd, then following the road to the future reservoir site. 

Project Status: The ringwall for the tank is completed. No further construction is scheduled until the tank is delivered around August 24, 2007.

 

Boulder Tank

 

12-inch Pipeline: Construction was completed on May 16, 2007.

 For additional information or EMERGENCIES, contact the information hotline at (760) 788-2204 or the Ramona Water District at (760) 789-1330.